North Urban Auckland flood recovery progress North Urban Auckland flood recovery progress
Extreme weather events in Tāmaki Makaurau / Auckland caused damage to roads in 2023.
Over the last 18 months, we’ve made significant progress on repairing storm-damaged roads in the North Urban Auckland area, as shown by the following statistics.
Reported sites and slip repairs as of 30 September 2024
- Total number of sites: 109 (38 major, 71 minor)
- Currently under construction: 9
- Completed sites: 88 (81%)
We have completed:
- 21 out of 38 major slips (55%)
- 67 out of 71 minor slips (94%).
There are 5 major slips currently under construction:
- Masterton Road, Rothesay Bay
- Spur Road, Stillwater
- Twin Wharf Road, Herald Island (2 sites)
- Duck Creek Road, Stillwater.
The reported number of sites requiring minor to major repairs will change slightly over time as the design and investigation of each slip site develops. We ask for your patience as we repair sites all over Auckland.
To report new issues, please contact us.
Completed slip repair sites
The following is a list of recently completed major sites in the North Urban area.
Work has also been completed on 67 minor sites, including hydroseeding with grasses to help stabilise the banks.
Our thanks go to everyone in each of these communities for your patience and understanding as we made necessary repairs and restored safe connections.
- Beach Road, Torbay
- Dairy Flat Highway, Dairy Flat (2 sites)
- East Coast Road, Redvale (one of 2 sites)
- Gills Road, Albany
- Glenvar Road, Torbay
- Hinemoa Terrace, Birkenhead
- Hobbs Road, Whangaparaoa
- Inkster Street, Birkenhead
- John Brian Drive, Redvale (site 1 of 2)
- Kaipatiki Road, Glenfield
- Mollyhawk Place, Birkenhead
- Paremoremo Road, Paremoremo (4 large slip sites)
- Ridge Road, Lucas Heights (2 sites and resilience work)
- Riverhaven Drive, Wade Heads
- Scott Road, Stillwater
- Sir Peter Blake Parade, Bayswater
- Tauhinu Road and The Close, Greenhithe
- Tizard Road, Birkenhead
Duck Creek Road, Stillwater
Road status: open, single lane with traffic lights operating
16 October 2024
The retaining wall on the southern side of the road is now largely complete. This week the team will be creating a temporary road surface for traffic to run on the other side of the road. We plan to work overnight on Sunday to move the barriers and equipment.
On Monday 21 October, the one-lane drive through area will switch from the north to the south side. Traffic will move to the inland side of the road next to the new retaining wall.
Watch aerial footage from September of the Duck Creek Road site (opens in a new tab).
27 September 2024
We have made good progress on the first retaining wall on the south side. Following investigations on site, the south side retaining wall will be extended a further 40m to stabilise the bank in this area. The team will switch over to working on the north side towards the end of October.
4 September 2024
The first retaining wall on the south side is progressing well. A crane is on site to hold up a power pole while we construct the retaining wall immediately below.
21 August 2024
Over the 6 weeks from 1 July, we have:
- cut back the embankment adjacent to number 307 Duck Creek Road
- installed 60% of the timber piles and 60% of the timber lagging (planks laid behind the piles) that make up the longest of the 3 retaining walls (95m).
In the coming weeks we aim to:
- relocate the nearby power pole and lines which were compromised during the weather event
- construct the road pavement on the newly widened section (adjacent to number 307 Duck Creek Road)
- switch traffic from the north (valley) side of the road to the newly widened south (embankment) side of the road
- commence construction of the smaller of the 2 north (valley) side retaining walls.
1 August 2024
Work is progressing well and is currently on programme, with completion expected in February 2025.
4 July 2024
Duck Creek Road remains open but is reduced to one lane of traffic through the work site.
27 June 2024
On 30 June 2024, work started between 296 and 325 Duck Creek Road, an area that was damaged by an underslip (slump below the road) during the Auckland Anniversary weather event in January 2023. Work includes:
- cutting back the embankment adjacent to 307 Duck Creek Road and creating a temporary widened road
- on the north (valley) side, constructing 2 timber retaining walls measuring 16 metres and 86 metres long
- on the embankment (south) side, constructing a 95-metre-long retaining wall adjacent to 307 Duck Creek Road
- finishing works such as pavement repairs, additional drainage, new kerb and channel, landscaping and fencing.
Duck Creek Road remains open but will be reduced to one lane of traffic through the work site. We will use a mix of temporary traffic management, such as temporary traffic lights, and a lower speed limit.
Hibiscus Coast Highway, Hatfields Beach
Road status: open, single lane with stop/go operating
11 October 2024
From Monday 14 October 2024, we will start repair work. We expect work to take 4 months to complete.
We will reduce Hibiscus Coast Highway to one lane with traffic light stop/go near the intersection with Ocean View Road.
First, we will upgrade drainage on the eastern side of the road. During that time, the single lane restriction will only be in place during work time.
From around 28 October (progress depending), we will install steel barriers. This is to enable works on the western side of the road.
We will then operate stop/go with traffic lights 24 hours a day, 7 days a week, for the remainder of the work.
Hibiscus Coast Highway was damaged by severe weather in early 2023.
We will also undertake some scheduled repairs on the other (eastern) side of the road at the same time.
Work includes:
- additional drainage, including a new kerb and channel on the eastern side of the road
- trimming trees and relocating services as part of enabling works
- constructing a 53m long reinforced concrete in-ground palisade wall with capping beam
- upgrading the footpath on the western side
- finishing works such as road pavement repairs and other improvements.
4 July 2024
Repairs to the slip near the Ocean View Road intersection will begin soon. A new concrete palisade wall will be built, with footpath improvements also planned. We are waiting for Vector and Chorus to give us plans showing poles and wires in the area.
John Brian Drive, Redvale
Road status: open, single lane
1 August 2024
Work on site 1 is now complete. We are currently finalising the design and pricing for site 2.
27 June 2024
There are 2 slip sites on John Brian Drive. Work at Site 1 began in June, and construction of the new retaining wall should be complete by the end of June. New kerb and channels as well as paving repairs will follow.
Design options for Site 2 are being finalised.
Masterton Road, Rothesay Bay
Road status: closed at the cul-de-sac end, residents access only
16 October 2024
Work is progressing well, despite the soft, muddy conditions. We have installed the timber piles. The team are now working on the timber lagging to support the road area.
Watch aerial footage taken during September of the Masterton Road work site (opens in a new tab).
27 September 2024
On 11 September, we started to repair the underslip at the bottom of Masterton Road in Rothesay Bay. We are building a new 27m long timber retaining wall and riprap (rock buttress) around the stream edge. The specialist team are working amongst the elements. Works are complicated by factors such as a recent king tide and soft ground conditions. Work is expected to take around three months and be completed in time for the summer.
11 September 2024
Work to repair the slip at the end of Masterton Road starts today and is expected to take approximately 3 months.
Masterton Road will be closed at the cul-de-sac end throughout the construction period, but access for neighbouring properties will be maintained. Pedestrian access to the beach will be maintained from the northern side of the road.
4 September 2024
Vector will install a temporary overhead power supply from Rothesay Bay Road to the Rothesay Bay toilet block by 7 September 24.
We will then be able to complete the flood remediation at the end of Masterton Road free from electrical hazards. Our work will be completed within 3 months. After we finish, Vector will return to remove the temporary supply and complete a final reinstatement.
Slip repairs will start soon. We will issue a notification letter to residents before repairs begin.
27 June 2024
Work to repair the underslip and wash-out at the end of Masterton Road near the beach will start soon. Repairs include:
- tree-pruning to enable works (this will be as minimal as possible)
- construction of a 27-metre-long timber retaining wall and riprap (rock buttress) near the footpath and edge of the stream
- finishing works such as road and footpath pavement and additional drainage facilities.
Pedestrian access to the beach will be maintained.
Rahui Road, Greenhithe
Road status: open with restricted access from either end, closed in the middle
Rahui Road was damaged during the Auckland Anniversary weekend weather event, January 2023. We plan to start work here on Monday 14 October 2024. We expect the project to take 3 months to complete.
Work to repair the under-slip includes:
- construction of a 45m long timber retaining wall
- finishing works such as road pavement repairs and new guardrail.
Rahui Road is closed between property numbers 14 and 16. Access for properties is via Rame Road or Marae Road.
Spur Road, Stillwater
Road status: open, single lane with traffic lights operating
16 October 2024
Work continues to progress well. The retaining wall is now complete. Pavement works are underway. We expect to install guardrails towards the end of the month.
Watch aerial footage taken during September of the Spur Road work site (opens in a new tab).
27 September 2024
Work on Spur Road is progressing well.
4 September 2024
Enabling work started 28 August 2024. A pre-start meeting was held on site 3 September 2024. The work is expected to take 3 months.
To repair the under-slip, we will construct:
- a 63m-long timber retaining wall
- finishing works such as road pavement repairs and drainage improvement.
All residents were advised via a letter delivery on 23 August 2024.
Spur Road will remain open and will be reduced to one lane of traffic through the work site. We will manage traffic with temporary traffic lights and a lower speed limit during construction.
26 June 2024
Spur Road was affected by a large slumping area during the Anniversary Weekend floods in January 2023. Repairs will start within the next few months.
The slip is near 230 Spur Road, and a new retaining wall will be built on the downhill side of the road (see image and map).
Twin Wharf Road, Herald Island
Road status: closed
16 October 2024
Pavement work is underway. We are constructing the asphalt surface this week. Planting also gets underway this week in collaboration with the local community.
Watch aerial footage taken during September of the Twin Wharf Road work site (opens in a new tab).
27 September 2024
Stages 1 and 2 are finishing soon along Twin Wharf Road on Herald Island. The final road paving reinstatement is scheduled for mid to late October. Following this, work on the new staircase will begin next to the toilets at the wharf. Topsoil will be placed early in October on the upper bank. We will then start planting with guidance from the local environmental group.
4 September 2024
Stage 1 of the slip remediation work started in May 2024 and is nearly finished.
We have:
- built a retaining wall on the embankment side
- stabilised the bank on the seaward side
- reinstated the footpath and carriageway.
Stage 2 of the slip remediation work started with the construction of a retaining wall adjacent to the temporary stairs. Before work continues, we will remove the temporary stairs.
Pedestrians will instead have to use the newly completed footpath along Twin Wharf Road after 2 September.
For Stage 3 we will construct a permanent stairway near the temporary stairs.
21 August 2024
Work continues on the timber retaining wall on the bank side of the road.
1 August 2024
Work on Twin Wharf Road is progressing well. The retaining wall on the seaward side of the road is now complete, and the team have begun work on pole installation on the bank side.
27 June 2024
In April 2024, enabling works started on Twin Wharf Road, Herald Island, where the road and footpath have slumped towards the water. Work here is expected to take several months to complete, as works will be conducted in stages.
Temporary stairs are in place to provide access while soil nails are being installed to stabilise the bank.
January 2024
Final design is being reviewed.
20 July 2023
Preliminary design is being reviewed.
3 May 2023
- We are doing geotechnical testing and drafting initial designs to build a new retaining wall to replace the wall that collapsed.
- We plan to begin construction in early 2024 and expect to be finished by mid-2024, weather permitting.
Wade River Road, Wade Heads
Road status: open, single lane
1 August 2024
We are currently finalising the design and price for the repairs. We are working with Vector, as they will need to move power lines and power poles before our work can begin.
January 2024
Design is being finalised.
20 July 2023
Design in progress.
25 May 2023
We are undertaking geotechnical testing and initial designs to build a new retaining wall to replace the damaged one. We plan to begin construction in early 2024 and, weather permitting, expect to be finished by mid-2024.
Other slip repairs
The following slip repairs are also on our list and currently in the design phase. We will share more information about each location under its own section when we have it. For now, other roads where slip repair work is planned include:
- Albany Heights Road, Albany Heights
- Brigham Creek Road, Whenuapai
- Bush Road, Albany
- East Coast Road, Red Vale
- Huka Road, Birkenhead
- Lannigan Street, Birkdale
- Lonely Track Road, Albany
- Raymond Terrace, Birkenhead
Please note: All works are subject to change due to factors such as weather, resourcing and delivery of supplies. Information contained here is a guide for general purposes only.