West Auckland flood recovery progress West Auckland flood recovery progress

Extreme weather events in 2023 caused damage to roads throughout Tāmaki Makaurau / Auckland. On this page, you can stay up to date on the progress of repair works in your area. 

West Auckland road updates

Not all sites are listed on this page, as some have already been repaired. Design work on others is still ongoing, and other roads will be added as we work through the programme. Works may be completed on some roads without being added to this page, depending on the scale of the work and the number of residents affected.

We ask for patience as we work to repair more than 2,000 sites across Auckland. 

To report new issues, please contact us.

Bethells Road 

Our contractor, Ventia, is putting the finishing touches on the Bethells Road repairs.

A new culvert was installed under the road, and drainage system improvements were made on both sides of the road.

Drainage culvert at the side of an unpaved gravel road lined with trees
Drainage system for the new culvert

Our contractor worked on 5 locations in the closed section. One of the major items was repairing a slip at the side of the road. By drilling in large soil nails, they were able to anchor this section back under the road. To secure the slip face and prevent water damage, they finished the surface with spray-on concrete. 

Three workmen in orange high-visibility jackets repair a roadside bank covered in black plastic tarp behind a metal guard rail
Construction workers drill soil nails into the slip face

The repair near Steam Hauler Track is also complete. The block wall has made the road safe, and improved drainage will make it more resilient for the future.

A block retaining wall set in a dirt bank alongside a rural road with a guardrail
Completed block retaining wall

Forest Hill Road, Waiatarua

Slip repair work outside 346 Forest Hill Road began in May 2024. The road is closed during works.

During the works, we discovered that power lines need to be moved. Vector will complete this work, but it will add to the length of the road closure.

Residents in the closed section of the road will have access to their property. The traffic management team will be on site to help you.

The construction team will repair the retaining wall and slip and replace the damaged kerb and channel.

  • Location: 346 Forest Hill Road, Waiatarua, Auckland (between West Coast Road and Kellys Road)
  • Work to be done: retaining wall, slip and kerb repairs
  • Start date: 13 May 2024
  • Hours of work: 7am to 7pm
  • Duration: until 25 September 2024 (weather dependent)

We plan to seal the road before we open it on Wednesday 25 September. Heavy rainfall in the last couple of weeks has made it challenging to get the road sealed. If we are unable to seal the road before 25 September, we will open it unsealed and come back when weather allows. We will be able to do this one lane at a time.

Glenesk Road, Piha

19 August 2024

Glenesk Road is now completed. Thank you to everyone for your patience.

A timber retaining wall along a grassy bank next to a creek
New retaining wall supports Glenesk Road in Piha

Huia Road – various sites

12 September 2024

There are multiple slip sites along Huia Road. We are looking for ways to keep one lane open on all sites while work in progress. We will update the community before works start on any of these sites.

81 Huia Road – We are rethinking the timing of these works after getting feedback from the community. Works will most likely start in January. We may also change the timing of other works on Huia Road.

370 Huia Road – We plan to start work on this site in December 2024 and finish by the end of January 2025.

634 Huia Road – Work will begin in February 2025 and is expected to be completed by the end of March 2025.

100m past Cornwallis Road – We plan to begin work in October 2024, and we expect the work to finish by December 2024.

100m past Kaitarakihi Road – Work will begin in March 2025. We expect to finish by the end of June 2025.

We are investigating one more site. Once the plan is confirmed, we will update the community about estimated work dates.

Huia Road slip site
81 Huia Road slip site

Karekare Road

23 September 2024

Karekare Road was closed on 19 August 2024 for slip repair.

Slip repair works have progressed well on Karekare Road and Lone Kauri Road. Works on the 2 remaining sites on Karekare Road (K4 and K5) will finish by December 2024. Our contractor is finishing up the first of these 2 sites. The second one is underway.

Once we have completed works on Karekare Road, Lone Kauri Road will be closed in January 2025 to complete one more site (L4).

Fulton Hogan working on slip site repair on Karekare Road
Works under way on Karekare Road
A slip site on Karekare Road

Kay Road, Waitākere

Closed - Residents and emergency services access only from Waitākere Road end.

Work is under way on the repair design.

While are unable to give a specific timeframe on repair works. We aim to restore this connection for the community in the first half of 2025.

Kellys Road, Oratia

16 October 2024

We started work on the slip repair on Kellys Road on 2 October 2024. Vector isolated the overhead powerlines during works.

We are now working on excavation and preparation works for the retaining wall. The road remains closed during works.

We expect works to take about 10 weeks to complete, depending on weather.

Excavation and benching in preparation for the new retaining wall.

Konini Road, Titirangi

23 September 2024

Repairs for Konini Road are in the design phase.

We do not plan to start works on Konini Road while Scenic Drive is closed. Konini Road repairs will start in 2025.

Lone Kauri Road, Karekare

14 August 2024

Karekare Road is closed for the rest of 2024 for slip repair.

Following Karekare Road’s completion, Lone Kauri Road will be closed in January 2025 to complete one more site (L4).

Lone Kauri site works
Lone Kauri site works
Work on Lone Kauri Road March 2024
Work on Lone Kauri Road March 2024

Mountain Road

16 October 2024

We are still on track to complete the 10 sites on Mountain Road by the end of 2024.

Each site has been named for its distance from Scenic Drive. For example, site 0.655 is 0.655km from Scenic Drive.

We have finished sites 0.655 and 0.712.

GSI completed the structural work on sites 1.833 and 1.664. Pavement repairs will start on these sites on 15 October 2024.

Repairs on site:

  • 1.833 will last for 10 working days, ending on 29 October 2024
  • 1.664 will last for 40 working days, ending on 12 November 2024.

GSI are currently working on sites 2.775, 1.468 and 1.387.

Repairs will take:

  • 40 working days on site 2.775, ending 8 November 2024
  • 30 working days on 1.468, ending 1 November 2024
  • 45 working days on 1.387, ending 6 December 2024.

We will be starting work on site 1.318 at the end of October. Repairs will take 35 working days, ending 6 December 2024.

We will start repairs on site 0.899 on 5 November 2024. Works will last 30 working days, ending 16 December 2024.

Our schedules for each site may change depending on final designs and weather.

We will keep you updated with any changes and provide updates on each site as we progress.

Map of slip repairs on Mountain Road.

We must consider that:

  • we can only work on 2 sites at any given time, due to the narrowness of the road and access through sites
  • in some places, road layouts might make it too unsafe to work on 2 sites at once
  • site designs must be approved before works can start, and work on some of these designs is still ongoing
  • although we have built some flexibility into the timeline, weather and other factors may cause delays.
7 construction workers, 2 large flat-bed trucks and a crane at a roadside work site. One man in a basket hoisted by the crane is working on a steep hillside slope covered in mesh and dotted with evenly spaced white squares.
Mountain Road works include soil nails and shotcrete to stabilise the road

Ngaio Road, Waima

23 September 2024

We are doing geotech monitoring on Ngaio Road and working on the repair design for this slip. A section of the road is coned off, though a newly created pedestrian path will keep people safe and keep vehicles off the damaged section.

Because we need to provide safe passage for pedestrians, we have had to extend the pedestrian walkway onto the road. This has narrowed the carriageway to around 4 metres, which is not enough space for 2 lanes and offers no visibility for giving way. Please use the detour route.

Part of the cyclone recovery, this work is scheduled for the first quarter of 2025.

Paturoa Road, Titirangi

23 September 2024

The road is closed around number 15, and work is continuing on the repair design for this road. Below is some information about the damage at this site.

We are currently working on 2 design options. Once the final design is confirmed, we will programme the start of works. We expect works to start in the first half of 2025.

Paturoa Road Slip
Paturoa Road slip

Piha Road

Works on the slip site at 73 Piha Road were completed in December 2023.

Retaining wall under works
Retaining wall under works

Rayner Road, Piha

31 July 2024

47 to 49 Rayner Road, Piha

Flexi-posts have been installed to keep vehicles away from the slip side of the road. The weight restriction is lifted. Our contractor is continuing to monitor this section of the road.

Flexiposts installed on Rayner Road, March 2023
Flexi-posts installed on Rayner Road, March 2023

Scenic Drive, near Arataki

12 September 2024

Works near 412 Scenic Drive, Waiatarua, are close to completion. The slip is located between West Coast Road and Arataki Visitor Centre.

We will open this site on Tuesday 17 September. Contractors will then start work on 2 other slips between here and Arataki Visitor Centre. The road will remain closed while the work takes place. Residents on the Piha/West Coast Road side of the closure will have access from the West Coast Road end.

Roadworks crew resurfacing a road behind a retaining wall with matting and seeding in place
Matting and seeding in place on the retaining wall alongside the road being rebuilt

Slips in both of these locations affect half the width of the road. The machinery used in the repairs will sit on the remaining section of the road.

At this stage, we expect these sites to be completed by the end of February 2025.

Traffic cones mark a recently resealed crack at the side of a rural road surrounded by trees

Traffic cones mark a recently resealed crack a the side of a rural road surrounded by trees
Slip sites on Scenic Drive between Arataki Visitors Centre and West Coast Road

19 August 2024

Works on this section of Scenic Drive are in their final stages. The wall and backfilling are completed, with the beam along the top of the wall still under construction. The road will then be rebuilt with the sub-base and base, then the road surface will be relayed.

We expect works on this section to be complete in early September, with the road reopening at this time. Please note that there are 3 more slips between this section and Shaw Road. The road is likely to be closed when works begin on those sections.

Retaining wall and backfill on a dirt and gravel rural road
Backfill behind the retaining wall complete, with a beam being built along the top of the wall
Slip at 412 Scenic Drive
Slip at 412 Scenic Drive

Scenic Drive, near the Auckland City lookout

12 August 2024

Work on this slip repair has been completed, the road is now fully open. Thank you for your patience during the repair work.

 

Digger and crew working on roadside slip repair
Work on stabilising the slip to secure the road

Truck and digger at a roadside work site surrounded by trees. A steep embankment on the left is covered with mesh.
Works almost complete at this slip site

Scenic Drive, North Swanson

23 September 2024

Drainage and road repair works are under way on Scenic Drive North, between Rangimarie Road and Puketaha Road. This work will be under way until early October.

Works will take place during the day and stop/go traffic management will be in place. There will be access through, no detour route needed.

Drainage works in progress on Scenic Drive, North Swanson

Scenic Drive, Titirangi 

23 September 2024

We are working on the third section of retaining wall. This wall will be 76m long and will join the first 2 sections together. We have installed 30 out of the 50 piles for this retaining wall.

We are also working on a repair to the embankment above the road. Over winter this section deteriorated more. We are working with the property owners to stabilise this section and build a buttress wall to prevent further slips above the road.

We put together a behind-the-scenes video with our contractor, Fulton Hogan. To view the video, visit our Facebook page.

A repaired road with roadside barriers at the side. Construction workers in high visibility jackets are constructing a footpath and retaining walls.
Early August, work behind the new retaining walls, the road has been repaired and the footpath is under construction.

Update on timeframe for Scenic Drive, Titirangi – 8 August 2024

The timeframe for slip repairs to Scenic Drive, Titirangi has changed. Originally, we were working on 2 major slip repairs. During works we decided to fix a third damaged section 76m long that has not collapsed yet, but will slip if the road is open to traffic.

The first 2 sections are almost 90% complete. However, we have experienced delays in the design for the third section. There has been some complexity in getting the structural components of the wall design correct. This element is essential as the road must withstand the load of heavy vehicles. This design delay has deferred the start of construction of the retaining wall.

Our contractors have begun rock scaling the embankment above this section of the road. Rock scaling involves working on abseiling equipment to assess the stability of the embankment, and to remove any unstable sections or rocks from the rockface.

We undertook a geotechnical assessment of the embankment above the road corridor. We discovered a section of the embankment which is at risk of failure. There are large fissures, or cracks, in the rocks and there is potential risk that this will collapse onto the road. We are planning to build a buttress wall to protect the road from this embankment. Although this damage is not on AT property, we will need to address this risk before the road can be opened.

This section of road between Woodlands Park Road and the roundabout will now be closed until late December 2024. We know this will be an additional disruption to the community.

This section will remain closed to pedestrians and cyclists. Kohu Road will remain closed at the Scenic Drive end, except to pedestrians and cyclists.

Impact on bus routes: School buses will continue to take the detour, and the shuttle bus will continue to serve Woodlands Park Road until the road is open.  

The following bus routes are affected by the closure:

Bus Route Number Changes

Glen Eden Intermediate

073 and 074

Green Bay High School

075 and 076

From Monday 4 March, school bus routes and times will start 10 minutes earlier in the mornings to accommodate the detour. You should also expect the bus to arrive back a little later due to the detour.

Public Bus Route 171

From midday 27 February, the 171 bus will service Laingholm only, following the usual route, but will miss Woodlands Park Road and take Huia Road to and from Titirangi

A shuttle bus service will meet the 171 bus in Titirangi to transfer passengers to and from Woodlands Park Road bus stops during the closure of Scenic Drive. 

A shuttle bus timetable is available. Please note: This timetable is based on approximate travel times. We recommend arriving at your bus stop on the earlier side.

Detour route

During the works, this section of Scenic Drive will be closed. The detour route will be along Woodlands Park Road and Huia Road, as shown in the map. We understand the inconvenience this may cause and ask drivers to plan ahead and allow extra time. 

Detour route

We’ve received questions from the community about the detour route and have put together some FAQs about Scenic Drive, Titirangi (PDF 148KB).

Scenic Drive, Waiatarua (elevation site)

30 May 2024

Road repair works at this site are complete, and the road is open both ways. We are pleased to have this important connection open for the community. We will do a final road reseal when other drainage works in this area are finished.

Scenic Drive, Waiatarua
Scenic Drive, Waiatarua, open in both directions

What happens next?

Final design plans are progressing for this site. A series of fan drains will be installed to reduce pore pressure from within the slip. Residents who have properties within the slip site have been contacted, and we are discussing the fan drain option with them. This final stage of repair works will include work across private properties, so this is an important part of the planning process. 

Simpson Road

113 Simpson Road – repair is in the design phase.

  • A road subsidence has occurred and extended approximately 107 metres in total length, with 77 metres of significantly affected carriageway. The failing retaining wall is along the edge of the road, on the downslope side.
  • Cracks have been sealed, and temporary traffic management will be in place until repairs are complete.

We will continue to monitor the site until permanent repairs start.

Takahe Road, Titirangi

23 September 2024

The block wall has been installed, and the team is working on repairing the road and pavement. This site is continuing to progress at a good pace.

We will seal the road when we have dry weather. Once we seal the road, we will open it one-way while we complete the rest of the works.

We are also:

  • completing the top of the block wall, including a rail
  • installing gabion baskets of rocks at the base of the wall
  • finishing planting.
Large block retaining wall at construction site with crew and digger
Takahe Road block retaining wall has been installed

Full road closure

Work to repair the slip near 32 Takahe Road has started.

A road closure between 2 and 42 Takahe Road will be in place. Residents who live within the road closure can access their homes using the following detour.

  • Properties west of 32 Takahe Road should use Otitiori Bay Road to Wood Bay Road.
  • Properties east of 32 Takahe Road should use Castleford Street to Avonleigh Road.

Otitori Bay Road is now open for the community access their homes.

Where

Takahe Road, Titirangi

When (start date)

19 June 2024

Hours

24-hour full road closure

For (duration)

Until early October, at which time we will be able to open one lane.

Pedestrian access  

We will provide pedestrian access through the site.

Te Henga Road

Work on Te Henga Road began on Monday 19 August. The slip is located near the intersection of Te Henga and Falls Roads.

The road will be closed from 60 to 66 Te Henga Road. During the closure, our contractor, Fulton Hogan, will be working with affected residents.

For those in the community who use Ministry of Education school bus services, your schools will be in touch about planned service changes during the closure.

A digger working on a dirt bank next to a cone-off road lined with trees
Excavation on Te Henga Road slip site

We will construct a retaining wall to support the road.

We have:

  • cleared vegetation
  • excavated the site
  • established the piling platform.

Work at this site has been challenging. Recent weather has meant there is more groundwater.

The batter slope has been also challenging, as it has been failing. We installed a temporary sheet pile wall to protect the site. We installed 42 sheet piles. It is likely we will need to install a further section to prevent the slope from failing.

This work and weather delays are likely to add 2 to 3 weeks to the programme of works at this site. This will extend the closure to mid-November, weather and ground conditions permitting.

Wairere Road

On 14 October 2024, Fulton Hogan started repairs near 349 Wairere Road. We will need to fully close the road while these works are in progress, as machinery will block the remaining lane. Past this section of Wairere Road, residents will not have access to Jonkers Road, Mildon Road or Horsman Road.

Once we have completed the first section of the repairs, we hope to open one lane to traffic.

To allow people to drive in and out, we will open the road for 5-minute windows at set times throughout the day. For information about the closure, including the timetable for openings, download the Wairere Road closure FAQs (PDF, 765KB).

Emergency access: Our contractor will work with emergency services to allow access in case of emergency. 

Contact us with your email address

We understand that this will be a challenging time for residents. We are creating an email list so we can communicate with everyone affected by this work. Please email us at atengagement@at.govt.nz.

Waitākere Road Bridge underpass closed

The underpass is closed at the bridge at the intersection of Waitākere Road and Bethells Road.

We have installed extra crossing signs and hit sticks on the approach to Bethells Road Waitākere Road (township end) to improve visibility and safety.

On 1 April 2023, the speed limit was lowered to 60km/hr near the intersection (between 190 metres north of Bethells Road and 220 metres south of Township Road).

Photo showing the additional signs and hit sticks that have been installed on Waitākere Road Bridge
Another photo showing the additional signs and hit sticks that have been installed on Waitākere Road Bridge
Additional signs and hit sticks installed in February on Waitākere Road Bridge

6 September 2024

We are currently designing the repair to the underpass. It is not safe for pedestrians to use.

We will update you when repair works begin.

The bridge is also scheduled for scour protection works. We will check if there have been changes to the stream bed below the bridge and make any necessary repairs.

Woodlands Park Road, Waima

23 September 2024

Work on the repair design is progressing. As this road is part of the detour route for Scenic Drive, we will schedule the repair work after the Scenic Drive link to Titirangi reopens.

Due to the nature of this slip, we plan to begin work in the drier months and will likely start in early 2025.

Woodlands Park Road slip site
Woodlands Park Road slip site